一、塑石假山施工准备
First, plastic stone rockery construction preparation
1、根据施工总平面图,进行场地整理,畅通道路,对实地进行勘查,复核标高及与周围建筑的相互位置关系,对施工生活用水、施工用电、场内临设用房等进行统筹合理安排。
1, according to the construction plan, site arrangement, smooth road, exploration of the field, check the elevation and the positional relationship with the surrounding architecture, construction of water, electricity, construction of temporary housing for the reasonable arrangement.

2、施工前,施工管理人员准备好安全牌、安全禁令牌以及七牌一图、施工现场的各管理物品,及消防器材。
2, before construction, the construction management personnel ready safety card, security ban card, and seven cards, a map, the construction site of the management of goods, and fire equipment.
3、落实技术资料,在施工图纸接到以后,立即组织有关人员熟悉施工图,在看图时必须抓住主要施工图环节,尽量在施工图纸会审得到解决,减少今后有施工时出现的设计变动,以便组织施工。
3, the implementation of technical information, after receiving the construction drawings, immediately organize relevant personnel to be familiar with construction drawings, in the picture must grasp the main construction link, to be solved in the construction drawings and design changes have reduced the construction in the future, in order to organize construction.
4、开工前,施工人员准备好施工质量评定表,施工日记等有关书面资料及标准管理各种台帐资料。
4, before construction, the construction staff prepared the construction quality assessment form, construction diary and other relevant written materials and standards, management of various accounting data.
5、落实施工机械提高现代化施工水平。
5, the implementation of construction machinery, improve the level of modern construction.
二、塑石假山施工组织部署
Two, plastic stone rockery construction, organization and deployment
1、施工组织以假山制作安装为主线进行施工,工作主要定位放样、塑石假山基础开挖、预埋件埋置、骨架焊接制作、钢丝网片焊接制作、钢丝网片绑扎、一层抹灰 、二层抹灰 、三层抹灰 、造型 、颜料面油。
1, the construction organization to the production and installation of the main line of rockery construction, main positioning lofting, rockery foundation excavation, buried, embedded frame welding production, steel wire mesh, welded wire mesh, making a layer of plaster, lashing two layer, three layer plastering plastering, shape, surface oil paint.
2、各分包施工班组无条件服从施工总计划。
2, sub contractor construction team unconditionally obey the construction master plan.